Underground development has commenced for the stage 1 exploration phase. Development will consist of two ore drives and dedicated drill drives to provide drilling platforms to enable infill drilling to be completed. Once completed, this drilling will allow a reserve estimate to be carried out. Currently there are no ore reserves at Red October. The drilling from surface is not of sufficient density to allow a confident ore reserve to be estimated, the stage 1 phase will not only provide drilling locations from underground but also a bulk sample of the mineralisation for processing at the Carosue Dam plant. Surface drilling is restricted by the deposits location on Lake Carey.
A total program of 30,000m of underground diamond drilling has been planned. This drilling will commence later in 2011 when development of the first drill drive has been completed.
View of the Red October pit with planned stage 1 underground development and proposed drill holes in red.